SRE should be part of change/RFC approval process for all changes getting released to the production.
Go / No go decision will be made before production release date by SRE release management and business, based on Quality gates artifacts, Custom Reports, Known Issues etc..
Criteria Go / No Go | Responsible | Status |
---|---|---|
All Blocker/Critical issues resolved |
SRE |
|
All Security Critical and High Items addressed |
Project Teams |
|
UAT Testing Signed Off |
Project and Business Teams |
|
Go-Live Task List In-Place |
SRE |
|
MOP prepared and reviewed |
SRE |
|
Go-Live Resources scheduled |
SRE/Project |
|
Business setting/configurations prior Go Live |
Project |
|
Communications Plan Developed and ready to execute |
SRE |
|
Rollback plan prepared & reviewed |
Project/SRE |
|