Release Approval Process

Published date: April 15, 2024, Version: 1.0

SRE should be part of change/RFC approval process for all changes getting released to the production.

Go / No go decision will be made before production release date by SRE release management and business, based on Quality gates artifacts, Custom Reports, Known Issues etc..

Criteria Go / No Go  Responsible Status

All Blocker/Critical issues resolved   

SRE

 

All Security Critical and High Items addressed  

Project Teams

 

UAT Testing Signed Off  

Project and Business Teams

 

Go-Live Task List In-Place  

SRE

 

MOP prepared and reviewed

SRE

 

Go-Live Resources scheduled

SRE/Project

 

Business setting/configurations prior Go Live

Project

 

Communications Plan Developed and ready to execute

SRE

 

Rollback plan prepared & reviewed

Project/SRE